Jan 05, 2014
  • Propellant filling operation of GSLV-D5 Strap Ons is completed

Jan 04, 2014
  • Propellant filling operation of GSLV-D5 Strap Ons is under progress

  • Preparations for Propellant filling operation of GSLV-D5 Strap Ons is under progress

  • GSLV-D5 Second Stage (GS2) Propellant filling operation is completed by 18:00hrs (IST)

  • GSLV-D5 Second Stage (GS2) Propellant filling operation is under progress

  • Preparations for GSLV-D5 Second Stage (GS2) Propellant filling operation commenced at 11:48 hrs (IST)

  • The 29 hour countdown started at 11:18 hrs (IST) and is in progress

Jan 03, 2014
  • 29 hr countdown is set to commence on Jan 04, 2014 at 11:18 hrs (IST)

Dec 28, 2013
  • The Mission Readiness Review (MRR) team and the Launch Authorisation Board (LAB) have cleared the GSLV-D5/GSAT 14 launch at 16:18 hrs (IST) on Jan 05, 2014

  • The vehicle is moved from the vehicle assembly building to the umbilical tower (the launch pad) in the morning of Dec 28, 2013

  • A 29-hour countdown is set to commence on Jan 04, 2014 at around 11 hrs (IST)

Home  |  About Us  |  ISRO Centres   |  Launch Vehicles  |  Satellites  |  Ground Facilities  |  Our Chairman
Related Links   |  Sitemap   |  FAQ   |  Feedback   |  Terms of Use   |  Privacy Policy  |  Contact Us  |  Disclaimer
Copyright 2008 ISRO, All Rights Reserved.
 
Best viewed with a resolution of 1024x768 with Internet Explorer 7.0