Abstract
In this paper, we consider a project-based organization that deals with an assignment problem in which a set of projects must be assigned to a group of project managers. This assignment is done based on the relative contributions of projects to the organizational mission and a matching score between each pair of a project and a project manager. We assume that some projects are deterministic, and the organization has signed their corresponding contracts while others are stochastic, i.e. the organization has submitted bids for these projects and may or may not win them in the future. Furthermore, we consider a finite planning horizon and presume a predetermined start time for each deterministic and stochastic project. We develop two models including a multi-stage stochastic integer programming model and a stochastic dynamic programming model to solve the problem. The latter shows better performance for small-size and less complex instances whereas the former gives better performance for more complex instances. We also developed a heuristic algorithm to solve large-size and more complex instances. Computational results indicate that the developed heuristic algorithm can reach near-optimal solutions in reasonable CPU run times and dominates the two other solution approaches particularly for large-size instances.



















Similar content being viewed by others
References
Albareda-Sambola, M., Vlerk, M. H., & Fernández, E. (2006). Exact solutions to a class of stochastic generalized assignment problems. European Journal of Operational Research, 173(2), 465–487.
Castanon, D. A., & Wohletz, J. M. (2009). Model predictive control for stochastic resource allocation. IEEE Transactions on Automatic Control, 54(8), 1739–1750.
Crawford, L., Hobbs, B., & Turner, J. R. (2006). Aligning capability with strategy: Categorizing projects to do the right projects and to do them right. Project Management Journal, 37(2), 38–50.
Dvir, D. O., Sadeh, A., & Malach-Pines, A. (2006). Projects and project managers: The relationship between project managers’ personality, project types, and project success. Project Management Journal, 37(5), 36–48.
Fricke, S. E., & Shenbar, A. J. (2000). Managing multiple engineering projects in a manufacturing support environment. IEEE Transactions on Engineering Management, 47(2), 258–268.
Hadad, Y., Keren, B., & Laslo, Z. (2013). A decision-making support system module for project manager selection according to past performance. International Journal of Project Management, 31(4), 532–541.
Hauschildt, J., Keim, G., & Medcof, J. W. (2000). Realistic criteria for project manager selection and development. Project Management Journal, 31(3), 23–32.
Heydar, M., O’Reilly, M. M., Trainer, E., Fackrell, M., Taylor, P. G., & Tirdad, A. (2022). A stochastic model for the patient-bed assignment problem with random arrivals and departures. Annals of Operations Research, 315, 813–845.
IPMA. (2015). ICB-IPMA competence baseline version 4.0. Nijkerk: International Project Management Association
Kang, K., Shanthikumar, J. G., & Altinkemer, K. (2016). Postponable acceptance and assignment: A stochastic dynamic programming approach. Manufacturing & Service Operations Management, 18(4), 493–508.
Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kuhn, H. W. (1955). The Hungarian method for the assignment problem. Naval Research Logistics Quarterly, 2(1–2), 83–97.
LeBlanc, L. J., Randels, D., & Swann, T. K. (2000). Heery International’s spreadsheet optimization model for assigning managers to construction projects. Interfaces, 30(6), 95–106.
Müller, R., & Turner, R. (2010). Leadership competency profiles of successful project managers. International Journal of Project Management, 28(5), 437–448.
Oliveira, E. C., Alencar, L. H., & Costa, A. P. (2018). Decision process of allocating projects to project managers. Production Planning & Control, 29(8), 645–654.
Palmowski, Z., & Sidorowicz, A. (2020). An application of dynamic programming to assign pressing tanks at wineries. European Journal of Operational Research, 287(1), 293–305.
Patanakul, P. (2011). Project manager assignment and its impact on multiple project management effectiveness: An empirical study of an IT organization. Engineering Management Journal, 23(4), 14–23.
Patanakul, P., Milosevic, D. Z., & Anderson, T. R. (2007). A decision support model for project manager assignments. IEEE Transactions on Engineering Management, 54(3), 548–564.
Pentico, D. W. (2007). Assignment problems: A golden anniversary survey. European Journal of Operational Research, 176(2), 774–793.
Pinedo, M. L. (2016). Scheduling: Theory, algorithms, and systems. New York: Springer.
Pinto, J. K., & Slevin, D. P. (1987). Critical factors in successful project implementation. IEEE Transactions on Engineering Management, EM-34(1), 22–27.
Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7 ed.). Newtown Square, PA: Project Management Institute
Russell, L. (2015). Project management for trainers. American Society for Training and Development.
Seboni, L., & Ssegawa, J. (2022). Does a project manager assignment process affect project management performance indicators? An empirical study. Sustainability, 14(13), 7637.
Varajão, J., & Cruz-Cunha, M. M. (2013). Using AHP and the IPMA Competence Baseline in the project managers selection process. International Journal of Production Research, 51(11), 3342–3354.
Ward, S., & Chapman, C. (1988). Developing competitive bids: A framework for information processing. Journal of the Operational Research Society, 39(2), 123–134.
Xu, Y., & Yeh, C. H. (2014). A performance-based approach to project assignment and performance evaluation. International Journal of Project Management, 32(2), 218–228.
Xue, M., Fu, C., & Yang, S.-L. (2020). Group consensus reaching based on a combination of expert weight and expert reliability. Applied Mathematics and Computation, 369, 124902.
Yang, J., He, F., Lin, X., & Shen, M.Z.-J. (2021). Mechanism design for stochastic dynamic parking resource allocation. Production and Operations Management, 30(10), 3615–3634.
Zavadskas, E. K., Turskis, Z., Tamošaitiené, J., & Marina, V. (2008). Multicriteria selection of project managers by applying grey criteria. Technological and Economic Development of Economy, 14(4), 462–477.
Author information
Authors and Affiliations
Corresponding author
Additional information
Publisher's Note
Springer Nature remains neutral with regard to jurisdictional claims in published maps and institutional affiliations.
Rights and permissions
Springer Nature or its licensor (e.g. a society or other partner) holds exclusive rights to this article under a publishing agreement with the author(s) or other rightsholder(s); author self-archiving of the accepted manuscript version of this article is solely governed by the terms of such publishing agreement and applicable law.
About this article
Cite this article
Rezaeian, A., Koosha, H., Ranjbar, M. et al. The assignment of project managers to projects in an uncertain dynamic environment. Ann Oper Res 341, 1107–1134 (2024). https://doi.org/10.1007/s10479-024-05958-x
Received:
Accepted:
Published:
Version of record:
Issue date:
DOI: https://doi.org/10.1007/s10479-024-05958-x